+1 917 8105386 [email protected]

chicken eggs farm

In this first exercise you are going to create the initial steps of a schedule. Begin with selecting something with which you are familiar - planning a flight, getting ready for an event...something that will require approximately 10-15 steps (For the purposes of this exercise, each step should be on one day). List the activities in order (sequence). Put a start and finish time on each activity. Put the activities into a graphic form (you can use the gantt chart view of MSP or use excel for this portion). Create at least 3 summary tasks and indent them so that they are at Level 2 of the schedule Create at least 3 detailed tasks under at least two of the summary tasks so that they are at level 3 Set the project start date Create Dependencies - make the tasks start to finish. Go to the Calendar and choose 2 days to make them Non-Working and make one weekend working days Create 2 milestones Assign 3 resources to various tasks

Ready To Get Started?

GET STARTED TODAY