explain the figure

Look at Figure 16.1 and 16.2 and answer the following questions: Which projects are behind schedule and over budget? explain Which projects are on schedule and under budget? explain Which projects are ahead of schedule but over budget? Explain For the project called “web-based cash flow” explain why it is marked as under budget using the terminology in the cost summary report (PV,EV,..,BAC, EAC, etc.